Project Overview:In order to increase the load, the reconstruction project of Shandong Huaneng Power plant was strengthened and repaired first.
Strengthen Method:carbon fiber wrapping strengthen
Material selection:anchoring epoxy resin adhesive , steel jacketing adhesive , high strength grout material
Process of Technology:drilling → cleaning →adhesive injection → screwing in steel bar or screw → curing
Shandong Huaneng Power Plant Company manages and operates 20 thermal power plants, 26 wind farms, 28 photovoltaic power plants, 2 biomass power plants, 5 energy storage power plants, 7 heating companies, 1 port enterprise and 4 subordinate enterprises